1.0
Comprehensive maintenance contract
for Control and Distribution systems.
Cleaning,
re-conditioning and testing e.g. fixed and moving auxiliary contacts, fixed and
moving main contacts, operating shaft, tripping shaft, etc. for power panel.
After cleaning / reconditioning / replacement of the
spare parts while reassembling the following jobs are also required to be
carried out.
i.
Greasing of mechanical components as
per greasing schedules and use of grease as recommended by OEM manuals.
ii.
Testing for closing and tripping
mechanism including adjustments / repairs. If needed.
iii.
Inspection / adjustment of fixed and
moving auxiliary contacts.
iv.
To check alignment and change if
required fixed and moving parts of ACB and change over main isolating contacts,
secondary isolating contacts, shutter assembly and telescopic.
v.
Checking, tightening and changing if
required of all accessories control wiring. Lugs terminals, CT, etc.
vi.
Cleaning of the arc chutes and
replacements if required.
vii.
Testing and replacement of major
parts if required of ACB and change over e.g. pole assembly, FRCD mechanism and
ACB and change over terminals connected to bus bars links complete repairing of
ACB and change over if damaged.
The works mentioned in schedule at item no. 5(i) to 5(ii)
and 6(i) to 6 (ii) of Part-B are required to be carried out on need basis. The
quantities specified are tentative and may vary as per actual requirement
during the tenure of contract. The decision for replacement of these items
shall be taken by Railway’s authorized representative based on the joint
inspection made by contractor’s representative and Railway’s authorized
representative. Payment for these items shall be made based on accepted rates
in respective quarterly payment due.